Monday, May 20, 2013

Final Blog

Trustees for the Town of Hot Sulphur Springs are accepting bids for bridge construction and thank you for your interest on this blog.  This will be our final entry, for further information call Sandy at Town Hall 970-725-3933.  We wish bidders the best of luck and look forward to a productive and safe construction season.

Friday, January 18, 2013

US Army Corp of Engineer's Permit Re-authorized

We are very pleased to report receipt of our wetland permit from the US Army Corps of Engineers, reauthorized on 10Jan13 under file # SPK-2009-01468.  See the attached file with Corps permit letter including details on mitigation and monitoring.  Important to note that in order to meet multi-agency requirements to minimize impacts to fish and wildlife, all work in the Colorado River and wetlands must be completed during the month of September and all work in riparian areas (essentially the entire project area) should be completed in September-November, and everything coordinated with Colorado Parks and Wildlife (previously the Colorado Division of Wildlife) who manage Pioneer Park as a State Wildlife Area.  Additional details will be included in the bid packets available soon. 

This paves the way for CDOT project approval after we cross a few more T’s and dot some I’s.  Thanks to everyone for their patience and continued support.